Current Schedule - Posted 3/14/2022:
This schedule is subject to change due to inclement weather or project delays and we will update accordingly.
Working Hours 7:00am-4:00pm/Single Lane Closure 9:00am-4:00pm:
Mon 3/14 – Inlet and Manhole repairs on (CR567) Old York Road, Township of Bridgewater, From North Branch River Bridge to Milltown Road
Tues 3/15-Fri 3/18 – Inlet and Manhole repairs on (CR620) Washington Valley Road, Township of Bridgewater, From Spring Run Lane to Mount Prospect Road
Road Resurfacing Working Hours 9:00am-4:00pm:
Tues 3/22- Thur 3/24 – Milling and Paving on (CR567) Old York Road, Township of Bridgewater, From North Branch River Bridge to Milltown Road
Fri 3/25- Thur 3/31 - Milling and Paving on (CR567) South Branch Road, Township of Branchburg, From Chubb Way to Pleasant Run Road
Road Resurfacing Working Hours 8:00pm-5:30am:
Fri 4/1 – Milling and Paving on (CR523) Main Street, Township of Bedminster, From Route 206 to Somerville Road
Fri 4/1 – Milling and Paving on (CR620) Washington Valley Road, Township of Bridgewater, From Spring Run Lane to Mount Prospect
Mon 4/4- Fri 4/8- Milling and Paving on (CR620) Washington Valley Road, Township of Bridgewater, From Spring Run Lane to Mount Prospect